Balad Water Project: A Step Towards A Better Future In Salah Al-Din... Work Continues At A Rapid Pace
Engineer Ya'rub Qahtan Al-Awad, Director General of Al-Fao General Engineering Company, stated that work continues on the supplementary works project for the Balad Water Project in Salah al-Din, which the company is implementing for the General Directorate of Water, while adhering to the latest international standards in execution.
Project Details
- Production Capacity: (4,000) cubic meters per hour.
- Beneficiary Areas: Balad District and surrounding areas, providing potable water.
- Implementation Period: (720) days.
- Cost: (62) billion Iraqi dinars.
Al-Awad added that the current work includes:
1) The four sedimentation tanks.
2) Buildings for the high- and low-pressure pumps, power system, and filters.
3) Preparing and transporting the structure for the (400) cubic-meter high-pressure tank.